Hale Family Clinical Building | Project Milestones

The following is the approximate project timeline for key phases of the proposed new clinical building.

  • Site Prep: Ongoing – 3rd quarter 2017
  • Excavation/Foundations: 3rd quarter 2017 – 4th quarter 2018
  • Steel/Concrete Superstructure: 4th quarter 2018 – 3rd quarter 2019
  • Building Envelop: 2nd quarter 2019 – 1st quarter 2020
  • Interior Fit-out: 2nd quarter 2019 – 4th quarter 2020
  • MEP Systems Start up/Testing/Inspection: 4th quarter 2020 – 2nd quarter 2021
  • Opening: 3rd quarter 2021